Floating Cover Maintenance - Layfield
Floating Cover Maintenance - Layfield LOCATION: Luray, VA TIMEFRAME: Summer/Fall 2004 SCOPE OF WORK: Maintenance of Hypalon Floating Cover & Hardware PROJECT PARTNERS: Owner: City of Luray Contractor: Layfield/CW Neal This existing cover was based on an outdated design and required diving inspection, temporary repairs, design support and upgrading of the cover to meet AWWA guidelines for drinking water floating covers. The project proceeded in two phases. Phase One: Dive inspection and documentation of existing facility Temporary repairs while the reservoir was in service In-depth report writing incorporating the design build system with the City of Luray, the cities consulting engineering firm and Layfield/CWN to bring the existing cover into compliance with AWWA suggested drinking wa