Case Study
First Stamford Place
PROJECT PROFILE WJE www.wje.com First Stamford Place Plaza Repairs | Stamford, CT CLIENT Empire State Realty Trust BACKGROUND First Stamford Place was designed by Welton Becket Associates of New York in 1985. The engineer of record for the project was Lev Zetlin Associates, Inc. First Stamford Place consists of three interconnected buildings constructed over a three- story cast-in-place concrete parking garage that encompasses the entire building site. Buildings 100 and 300 are similar seven-story cast-in-place concrete frame office buildings, and Building 200 is a four-story reinforced cast-in-place concrete frame office building. Concrete sidewalks, landscaping