Case Study

Felixstowe Branch Capacity Enhancement

Felixstowe Branch Capacity Enhancement

Pages 1 Pages

“1.4km track formation, embankment and ground stabilisation” Felixstowe Branch Capacity Enhancement Felixstowe Branch Capacity Enhancement Track Loop Embankment work T he Felixstowe Capacity Enhancement Scheme was a £60m Project as part of Network Rail’s Upgrade Plan which was funded by the Strategic Freight Network and Hutchinson Ports to increase the freight capacity to and from the Port of Felixstowe. Working closely with our client, we produced efficient phasing and logistics plans to ensure successful, timely and safe delivery, achieving the key bottom ballast installation date on the 22nd of September 2018. This earthworks project has seen the successful completion of 1.4km of new track formation including all ground stabilisation, drainage blankets and 8