Case Study
FATHOM Subsea Certi?ed Asphaltene Inhibitor Prevented Precipitation in Separator
Bene? ts ? Prevented asphaltene precipitation in the HP separator ? Lowered chemical treatment rates ? After full production was restored, the value of flowing the shut-in well was approximately $120,000/day Project background and challenges ? A methanol umbilical to a subsea well failed ? Getting the second well back online by commingling with a third higher pressure well ? The high asphaltene content of the third well was incompa