Case Study
Everything is brighter in Texas
BACKGROUND Led by the engineering, procurement, and construction (EPC) company Renewable Energy Systems (RES), solar trackers developed by Array Technologies were installed at the Lamesa Solar Facility in Lamesa, Texas – equidistant from Lubbock and Midland. Array’s flagship single-axis tracker, the DuraTrack ® HZ v3, was selected as the tracking product of choice to allow for maximum harvesting of clean, renewable solar energy at the 102 MW (ac) / 131 MW (dc) PV plant. The 887-acre solar plant generates enough electricity to help meet the energy needs of more than 15,000 Texas homes. OVERCOMING SITE CHALLENGES Almost immediately after groundbreaking, the Lamesa project faced unexpected meteorological challenges. Heavy rains threatened the delivery schedule and installation of