Case Study

Essity – Roll Handling Pits

Essity – Roll Handling Pits

33-35 SANDY LANE, SKELMERSDALE, LANCS, WN8 8LA T 01695 555065 E info@hawkinsconstruction.co.uk W www.hawkinsconstruction.co.uk Essity – Roll Handling Pits Programme: 1 week (Fastrack during shutdown) Form Of Contract: Essity Standard T&C’s Project Value: £60k Location: Essity, Stubbins Mill, Ramsbottom Project Description: • Hawkins where engaged to complete 2no. tissue roll handling pits. • The pits consisted of a reinforced concrete base slab and walls laid to slight tolerances for a new recessed conveyor system. • The area was a live site with product movements in and around the workspace taking place every 30 minutes during the excavation phase. This meant constant communication with the client and pla

Join for free to read