Eaton’s innovative modular substation helps Jemez Mountains Electric Cooperative quickly add capacity to meet customer demand Location: Blanco, New Mexico Challenge: Complete a major substation upgrade within an aggressive project timeline to meet signifi cantly expanding customer demand Solution: Eaton’s modular integrated transportable substation (MITS) and turnkey engineering support from substation design to assembly and delivery Results: A portable, expandable design in a compact footprint engineered to accommodate current and future power needs—designed, built, commissioned and ready to energize two months after breaking ground “Eaton’s modular substation design enabled us to meet our members’ evolving power requirements much faster than a traditional solution.”