Case Study
East Hills Elementary School Renovation
Location Roslyn Heights, NY Project Type K-12 Education Product Flint Light Marfim 24”x24”, 5mm Flint Light Grafite 24”x24”, 5mm Mosa Colors - Brilliant Blue, Golden Yellow, Butterfly Green, 6”x6” Glossy, Custom Cut Quantity 8,000 Square Feet (SF) Design Firm KG&D, Mount KISCO Tile Installer Baybrent Tile Project Area Corridors Challenge In May of 2014, Roslyn, New York voters approved a $41.3M capital programs bond for the Roslyn School District. With such a high dollar volume, each targeted school became a high-profile project, not just because they hadn’t been upgraded in decades, but because the bulk of the bond was tax-payer funded. This made transparency a must, with strict accountability to the budget and dollars spent. New concerns over infrastructure and safety measures m