Case Study
Earnest Pruett Technical School
Alabama Ram Jack www.alramjack.com | 877-875-2171 Bessemer, AL Ram Jack Stabilizes Unreinforced Masonry Retaining Walls Succumbing to Settling HOLDING Up THE HALLS OF LEARNING 2014 cASE study Type: Commercial | Issue: AL201406 RAM JACK LOCAtION:2 Alabama Ram Rack installed tie-back anchors in only two days using small, portable equipment. The anchors were grouted and allowed to cure for one week before Ram Jack tie-back plates were applied