Eagle Ford Gas Treatment Facility #2

Eagle Ford Gas Treatment Facility #2

Project Profile The Spartan Advantage www.spartanep.com Eagle Ford Shale Gas T reating Services, including inlet slug catcher, inlet filtration, after cooler and dehydrator, on-site generator for site power and thermal oxidizer 90 days October 2012 Contract Operations with service level guarantee Spartan installed a modular 100 GPM Amine Facility in four weeks. The site included all components necessary to treat high BTU gas found in emerging