E3000s Enlisted for Cold Weather Concrete Bridge Deck Curing (Tiverton to Portsmouth, Rhode Island) Time was of the essence. The only option was to make multiple bridge deck pours during the winter months spanning 2011 and 2012. “The contract used calendar days, so it did not matter if winter delayed us,” says Keith Catanzaro, superintendent for Cardi Corporation. If crews missed the May 11, 2012 target, “we would receive $16,500 per-day disincentive for every day beyond the deadline, so we could not miss our end date,” he added. (Tiverton to Portsmouth, Rhode Island) Time was of the essence. The only option was to make multiple bridge deck pours during the winter months spanning 2011 and 2012. “The contract used calendar days, so it did not matter if winter delayed us,” says Keith Catanza