Dutypoint case study: Elmbridge Court Roundabout
Dutypoint Ltd, Shepherd Road, Gloucester GL2 5EL T: 01452 300592 | sales@dutypoint.com www.dutypoint.com PROJECT NAME A40 Elmbridge Court Roundabout INDUSTRY SECTOR Construction PROJECT TYPE Highways CLIENT Gloucestershire County Council ARCHITECT Amey PROJECT VALUE £8 Million PROGRAMME 13 Months COMPLETION October 2017 PRODUCT SUPPLIED Pre-packaged pump station PROJECT SUMMARY Redevelopment of existing roundabout to improve traffic capacity. Additional lanes on all approaches and new hamburger lane to assist flow of traffic, new traffic signals and a new surface water drainage system. PROJECT CHALLENGE As with all highway projects, temporary traffic management causes extra challenges for all drivers and workers, not to mention the extra health and safety risks and the unpredicta