Dudwell Lane Halifax

Dudwell Lane Halifax

Pages 2 Pages

Dudwell Lane Halifax THE EARTH. UNDER CONTROL THE CHALLENGE: Time is of the essence when it comes to the Railways work, it is mainly done on night shifts or a possession, the section above firstly the vegetation had to be cut back then work could commence meshing and inserting bolts, this type of operation it is imperative that all materials are on site when required MINOVA APPROACH TO SOLVE PROBLEM: To secure the slope, Minova R38/500 Self Drilling Anchor were installed in 6 meter lengths, using 90 mm holes inclined at 20 degrees and Am1001 thixotropic high strength grout The R38/500 SDA’s were chosen as they would meet the requirements of high tensile strength at the same time as the large cross s