Case Study CFA Piling, Track RRV (Drilling and Civils), Movax, BSP Hammer Project Snapshot: Don Viaduct - Bridge Strengthening Rail Sector CFA Piling & Civils Project Case Study Project Background www.van-elle.co.uk 01773 580 580 info@van-elle.co.uk facebook.com/VanElleLimited/ @VanElleLimited linkedin.com/company/van-elle-ltd Techniques: 32 no. CHS 762mm 40 no. CFA 17.5m Solution: Client: BAM Nuttal In March 2019, we were successfully awarded the contract by BAM Nuttall’s HEP team to help on the Don Viaduct Bridge Strengthening in Aberdeen, originally built in 1880. The project was to install piles that would form part of a new shock absorber anchorage assembly that will allow the Don Viaduct to remain in use for many more years to come. Issue Our initial schedule of works included