Distribution Centre, Warrington

Distribution Centre, Warrington

Old rooflight outer sheet Replacement complete Before & after replacement Case Study – Distribution Centre, Warrington A whole new light; refurbishment using Zenon Evolution High Access Maintenance Limited undertook a 16 week project in Warrington on a distribution centre to refurbish the building and its roof. High Access offer a comprehensive high-level building maintenance and cleaning service for the commercial sector with their head office based in Greater Manchester. From here and their other branches in Scotland and in Slough, they undertake both emergency and planned projects nationally. This project involved a 8-12 person team over a period of 16 weeks, and included: • Supply and installation of safety netting and 1400lm of edge protection with 2no Haki stair towers • Rep