BUILT in 2009 FOR BY Burmeister & Wain Scandinavian Contractor A/S Dhekelia Power Plant, ICE I 50 MW, Cyprus BWSC - YOUR BEST PARTNER FOR GROWTH!The Electricity Authority of Cyprus (EAC) has experienced an increased demand of electricity in Cyprus. In this relation, EAC awarded BWSC a 3-phase contract consisting of one 50 MW Temporary Power Plant, one 50 MW Permanent Power Plant, and a 4-year TSA agreement at Dhekelia Power Station, Cyprus. Electricity Authority of Cyprus 50 MW ICE I Power Plant at Dhekelia Power Station Phase 1: Temporary Power Plant (TPP) The TPP was supplied, erected, and in full operation on the 1st of June, 2008 by BWSC and the Dutch subcontractor Energyst B.V. The TPP output was 50 MW generating for a period of 4 months during summer peak while constr