Design and installation of an elevated pressure gas meter rig to support the expansion of the University of Keele campus
Design and installation of an elevated pressure gas meter rig to support the expansion of the University of Keele campus
University of Keele Design and installation of an elevated pressure gas meter rig to support the expansion of the University of Keele campus. Programme Over recent years, the University of Keele has embarked on a far-reaching expansion programme for its campus and business facilities. With this growth came the need for an upgrading of the gas network that would not only meet current requirements but also take account of the university’s plans for the future. Energy Assets was called in to disconnect and remove an existing 11M medium pressure gas meter and supply and install a new 16M medium pressure twin stream rotary meter and associated pipework capable of managing a load of 4,003kWh at an elevated pressure of 28mbar. The work had the potential to cause significant disruption but through