Degassing And Decontamination of a Crude Unit

Visit our website for more Case Studies and Insights at: fourquest.com/case-studies fourquest.com/insights This was the first vapour-phase application where the entire crude unit was to be degassed and decontaminated simultaneously. Highlights: › 5x less chemistry required compared to traditional decontamination › No additional expenses associated with supplied air and associated PPE for manpower vessel entry › Reduced schedule over traditional cleaning methods Degassing And Decontamination of a Crude Unit CASE STUDY Previously, the client had broken down the unit into separate individual stages with each degassing operation taking place over 48-hours. Our process took 24-hours total; saving one day of outage time over an individual stage, and several days