Datwyler FDN-IR Splice Closure Used In Dietlikon FTTH Project
www.cabling.datwyler.com © 2014 Datwyler Cabling Solutions. All rights reserved. 1 In 2010, Datwyler was appointed to implement the FTTH pro- ject in Dietlikon as general contractor/joint contractor. The plan is to have the entire municipality connected up to FTTH by the end of 2014. This means that all 3700 households will receive a fibre optic connection. To ensure the provision of an efficient, high-performance infra- structure, Dietlikon Municipal Works Department decided to purchase virtually all its FTTH material from Datwyler. Almost all the components used are from Datwyler, from the cables in the feeder and drop area through the newly built FTTH head station (Point of Presence, PoP) and all the external sites li