Case Study
“Datwyler Data Centre Solution” For New Swisscom Data Centre
www.cabling.datwyler.com © 2015 Datwyler Cabling Solutions. All rights reserved. Top-right picture: Swisscom. The new data centre (DC) in Bern-Wankdorf, which repre- sents a Swisscom investment of around 60 million Swiss francs and was under construction for two years, opened in September 2014 and was fully operational by the end of the year. The DC currently occupies 4,000 square metres of usable space on four floors, with room for expansion as required, and houses approximately 5,000 servers with around 10,000 customer systems. It is one of the very few in Europe to have Tier IV certification guaranteeing optimum availability of data and systems. An innovative cooling concept enables it to achieve the best possible energy usage values. Most stringent technical stand