Our energy working for you. TM > Case History Emergency Prime Power Station, Zacatecas, Mexico Where: Two substation sites outside Zacatecas, Mexico What: A 170 MW emergency prime power system installed and commissioned on a very short timeline Purpose: Replace temporary de? cits in base-load hydroelectric power caused by record-low reservoir levels Primary choice factors: Rapid availability of multiple Rental Power units with high fuel