CSX Coal Loading System

JDRM The CSX coal loader project involved the total replacement of the 1957 power and control systems with new power distribution, motor control centers, solid state DC drives, programmable logic controllers and programming. The aging existing system consisted of exposed contactors and resistors on slate board. JDRM provided electrical engineering and served as the project manager with Designer’s Edge designing the controls and doing CSX Coal Loading System The Port of Toledo is one of the world's leading coal and iron ore facilities and the largest seaport by area on the Great Lakes. Originally built in 1957, the CSX Coal Loading System at the Port of Toledo needed updated controls and electrical feeds - - a complicated project which was completed in just 14 weeks.the programming. L