Crude Oil Management Program Increased Throughput

Crude Oil Management Program Increased Throughput

Pages 2 Pages

Case History Processing problems A North American re? nery experienced problems when they began processing increased levels of heavy Canadian crudes. The heavy crude formed an emulsion layer within the desalter and led to oil undercarry to the wastewater treatment plant (WWTP). For several weeks, the charge rates to the re? nery had to be reduced. The incumbent demulsi? er had been used for more than 10 years, but it was unable to meet