Case Study
Criterion Wind Park
Criterion Wind Park Criterion Wind Park New 34.5kV Collector System Garrett County, Maryland Realtime provided engineering for the construction of a new 34.5kV Collector System and the associated 34.5/138kV substation. The project provided an interconnection point for the installation and operation of a 70 MW wind park. The wink park consists of (28) 2.5 MW wind turbines in Garrett County, Maryland. Included in this project were design services f