Case Study
Cowdenbeath Wetlands - Barhale
Cowdenbeath Wetlands Barhale Main Contractor Barhale Client Scottish Water Building Type Remediation and associated earthworks Procurement Route Negotiated Tender Contract Award January 2014 Contract Completion March 2014 Anticipated Duration 60 Days Key milestones Formation of new visitor car park and access road to facilitate the works Construction of a new fire water storage pond for the distillery Construction of temporary suds and sur