Cooling Water Supply System for Energy Station, Sandy Creek Power Partners
19 18 Sandy Creek Power Partners managed construction of the Sandy Creek Energy Station, a nominal 900-MW, coal-fired electric generating station in Riesel, Texas. In 2008, FNI was contracted to assist with the design of a cooling water supply system for the new coal-fired plant. The system was required to transfer the Type II treated effluent from the existing chlorine contact basins at the Waco Metropolitan Area Regional Sewer System Waste