Case Study
Contour Mends Pinhole Leak on a Topside Weldolet
THE HIGH-PERFORMANCE CRITICAL INFRASTRUCTURE COMPANY Easy to Install | Cost Effective to Deploy | Durable for Decades Contour Mends Pinhole Leak on a Topside Weldolet PIPE DETAIL 10-inch (254-mm) pinhole leak at a weldolet on an oil line Essential line that could result in shutdown of the platform SUMMARY A pinhole leak at a weldolet on a 10-inch (254-mm) oil line needed repair Clock Spring Contour was applied to the leak and surrounding area 2 local Clock Spring trained technicians completed the installation in 2 days This repair allows the facility to operate safely until the next planned shutdown A pinhole leak resulting from internal erosion or a chemical reaction was discovered at a weldolet on a 10-inch (254-mm) line running from the south manifold to the HP separator on a platform o