“Connecting you to the grid ” Project Overview – Claredown Project Statistics Project: Claredown Location: Essex DNO: UKPN Voltage: 33kV Works Awarded: Contestable Works, BOP Completed: March 2018 SCOPE OF WORKS – BALANCE OF PLANT ? Detailed Electrical & Civil design works to include substation, compound, cable and drainage plans ? Earthing study and report, plus all site specific system studies and Geotechnical surveys and reports ? Supply and install of drainage and inspection chambers ? Supply and install of internal and external access roads ? Supply and install of security fencing ? Supply and install of the below ground Earthing ? Supply and install of all concrete foundations for the Battery Containers, Substatio