Case Study

Compressor Station Upgrade

Compressor Station Upgrade

Pages 1 Pages

An Employee-Owned Company | © 2015 Kleinfelder. All rights reserved. Gas development activity in the area prompted the need for increased gas gathering and processing capacity at an existing compressor station. Kleinfelder’s scope included project management, engineering, and procurement for a major increase in processing capacity. RESTRICTED ACCESS AND SCHEDULE This plant was located in Northern British Columbia in a winter access-only area with restricted ice bridge and winter roads. A 125-ton compressor package required a weight loss program to transport, with reassembly onsite. The construction window was January to mid March, creating a major logistical and scheduling challenge to avoid expensive air lifting of labour, equipment, materials, and supplies. COMPREHENSIVE INTE