CA SE STUDY Client: Combined Linen Services Location: T orquay, Devon Commencement: December 2001 Length of contract: 16-20 weeks Project type: Laundry Overview The overall project was managed by Adrian Clay who worked closely with Kannegiesser (machinery manufacturer) from the building design phase to ensure the installation went smoothly, there was a mix of new & used equipment installed with Clay & Abbott being responsible for the design of the services & utility delivery systems and the overall equipment installation. This project required special attention from our design team as the location of the installation was in a valley required the installation of a self supporting chimney Combined Linen Services - T orquay 1 2CA SE STUDY Combined Linen Services - T orquay 1: water tank & chi