Case Study
Combating Moisture Settlement in Wisconsin
THE CHALLENGE Roadway reconstruction over marshland in Wisconsin. JOB OWNER Jefferson County Highway Department ENGINEER Jefferson County Highway Department DATE OF INSTALLATION September 2013 Wisconsin Highway 106 (STH-106) was reconstructed over a marsh area approximately 3 years prior, and almost immediately began experiencing differential settlement issues. Jefferson County Highway Department desired a rapid solution for reconstruction that would minimize the over excavation volume of the wet, organic soils and still provide a firm construction platform for the flexible pavement roadway. In addition, the construction platform would need to be robust enough to reduce differential settlement along the roadway route to maintain a roadway surface with acceptable rideability. PRO