Case Study

City of Vancouver

City of Vancouver

Pages 4 Pages

Quick Project Facts Number of Facilities: 36 Total Project Value: $16.2 Million Total Energy Reduction: 79,000 GJ (24 per cent) Annual emissions reduction: 3,000 tonnes (28 per cent) Guaranteed Annual Utility Savings: $930,000 Avoided emissions offset costs at $25/tonne: $75,000 Power Smart incentives: $475,000 Project start date (Pilot): January 2006 Project completion: April 2011 The City of Vancouver, Ameresc