Chemical Treatment Plant Upgrade, Hyperchlorite Plant

Chemical Treatment Plant Upgrade, Hyperchlorite Plant

RESOURCES CHEMICAL TREATMENT PLANT UPGRADE, HYPERCHLORITE PLANT CLIENT: ORICA / LOCATION: WA YEAR: 2008 / SECTOR: RESOURCES DELIVERED ON TIME In 2008, Austline Fabrications fabricated, installed and commissioned an upgrade to Orica’s Hypochlorite Plant in Kewdale, Western Australia. When Austline was engaged, the project was running eight weeks behind schedule. Austline was offered an incentive if all components were manufactured, installed and commissioned within a tight 12 week timeframe. All components were delivered on time. SCOPE OF WORKS SMP Installation Works Thermoplastic piping Tank loading platform Installation of all valves, vessels, pumps, filters and instruments as required Backflow prevention devices SS, CS & Lined pipin