Case Study
Central Bedfordshire College - Engineering Centre
Introduction This exciting new facility for Central Bedfordshire College comprises double height ceiling reception and café area, teaching and demonstration spaces, teaching rooms, electronics/ computer workshops, a large machine workshop and welding facilities. This new engineering centre marks our sixth project with Central Bedfordshire College, providing dedicated employer-led engineering Central Bedfordshire College engineering centre This has been one of the best projects worked on with Ashe from start to finish. Barry Groves Central Bedfordshire College building better Case Study Chartmoor Road, Leighton Buzzard, LU7 4QG Duration 48 weeks Start 21.11.16 Finish 31.07.17 Value £3.3m Client Central Bedfordshire College Project Manager Project Management Solutio