Case Study
Center for the Intrepid
PROJECT PROFILE Center for the Intrepid Loca ti on: Builder: Architect: BT Supervisor: BT Project Manager: Scope: The Center was designed and built in 18 months. The fast track design build process compressed BakerTriangle’s schedule from 12 months to 8 months. Two-week look- ahead schedules were useful tools for the management team as they determined the best ways to accomplish the work. BT crews worked 6 days a week with an average crew