metadownhole.com Page 01 of 02 Case Study_Norwegian North Sea Operator Meta Casing Reconnect The client was able to regain well integrity and increase production by installing larger tubing and annular safety valves, whilst replacing the wellhead and retaining its original height. Challenge Following a sidetrack operation the window exit in the open hole was expected to be non-permeable, but was later found to be slowly charging the B annulus. Th