Case Study
Capital Coated Steel
Capital Coated Steel Cardiff Scope of Project: Relocation of 3 steel cut to length lines from one factory unit to another Trojan-Mek project managed new electricity supply (500 kVa transformer & 800A MCCB) from distribution company (WPD), design and installation of electrical distribution for new locations of lines, and civil works. Relocated 3 steel cut to length lines, each with a mandrel coil feed, leveller, edge trimmer,