Case Study
California Penthouse: VRF Zoning System Solves 15-Year-Old Comfort Challenge
case study www.mitsubishipro.com November 2014 California Penthouse: VRF Zoning System Solves 15-Year-Old Comfort Challenge San Diego, California Brue-Carstens Residence Project Location: San Diego, California Completion Date: September 2012 Project Team Owners: Sandra Brue and Chris Carstens HVAC Contractor: Sirius Mechanical, Inc., Moreno Valley, California HVAC Distributor: U.S. Air Conditioning Distributors, City of Industry, California Mitsubishi Electric Equipment Installed: (2) PQRY-P96THMU-A WR2-Series Water- source Condenser Units (2) PLFY-P24NBMU-E Ceiling-recessed Indoor Units (2) PLFY-P18NBMU-E Ceiling-recessed Indoor Units (6) PMFY-P12NBMU-E Ceiling-recessed Indoor Units (1) PEFY-P15NBMU-E Ceiling-concealed Ducted Indoo