C839 Lowestoft South Beach Toe Protection Scheme

C839 Lowestoft South Beach Toe Protection Scheme

Contract Summary: The Lowestoft Beach Protection scheme consisted of the design and installation of approximately 170m of toe protection to reinforce an existing Victorian flint sea wall. The toe protection comprised of 6.5m long steel sheet piles, which were driven seaward of the wall. The toe of the wall was connected to the piles with a 450mm thick reinforced concrete