Case Study

Boiler Installationat SAICA Paper Mill

Boiler Installationat SAICA Paper Mill

Boiler Installation at SAICA Paper Mill CUSTOMER: Aalborg Engineering LOCATION: Partington, Greater Manchester THE OPPORTUNITY In 2011, Aalborg Engineering approached Power System Services to install a HRSG boiler as part of the SAICA paper mill development. THE SOLUTION The project involved numerous key activities, not limited to the following: • Logistical support for the delivery of large boiler modules from eastern Europe. • Production of lift studies for both unloading and erection often using more than one crane and complicated lifting beam/ strong back arrangements to ensure no distortion takes place. • Temporary stabilisation of modules. • Structural steelwork erection. • Significant quantity of boiler shell welding. • Erection of low and high pressure site made and pre man