Black Mountain Reservoir
In 2012, a large diameter 42"/1050 mm transmission main was built to convey water to and from a planned UV Disinfection Facility located below the Black Mountain Reservoir. The Victaulic AGS grooved system was chosen to join the piping system located below existing roads where space was limited. Carbon steel coated and lined pipe was prepared on-site using a Victaulic VE872 motorized roll grooving tool. Black Mountain Irrigation District