BHGE frac plug combo accelerated milling, improved debris removal in Oklahoma well Challenges • Low bottomhole pressure caused significant lift issues, making cleanouts difficult • Accelerate plug milling and debris removal Results • Experienced zero motor stalls despite pumping 9.5 MMscf of nitrogen through the motor • Required zero short trips, avoiding NPT and excess cleanout costs • Improved hole cleaning • Enabled fast frac ball pump-down operations, landing balls at 15 bbl/min • Allowed for continued production from the lower zones A customer performing plug-and-perf completions on a low-temperature, low- pressure well in Oklahoma was looking for a way to accelerate plug milling and improve debris removal. Because of the low bottomhole pressure, the well had si