Case Study
Bearing Solution Avoids 10 Week Lead Time
Case Study Bearings Summary Industry: Paper and Board . Application: Bearing Actual Saving: £150.94 Payback Period: Bearing Solution Avoids 10 Week Lead Time Re-engineered bearing is on-site within a week ISSUE OTHER BENEFITS ? Improved delivery from 10 weeks to 7 days ? Bearing delivered to coincide with planned shutdown ? Cost saving on original part FURTHER COMMENTS... All of this was achieved within 7 days, and was on-site in