Barton provide flood alleviation works for new housing development

Barton provide flood alleviation works for new housing development

Pages 1 Pages

Barton provide flood alleviation works for new housing development Barton were contracted under Galliford Try to provide excavation of topsoil to agreed haul routes, mitigation ponds and reed beds as part of flood alleviation works at Stanton Cross development site in Wellingborough. We utilised GPS controlled machinery throughout the project. The site is under development from Bovis Homes, with an expected 3.650 homes, employment areas and shopping facilities planned across the site to rejuvenate Wellingborough. Scope of work: ? Top soil strip & excavation ? Flood alleviation ? 1500m haul road Location Wellingborough, Stanton Cross Development Client Galliford Try / Land and Water Value £300k Duration 12 weeks Quantity ? 9000m3 top soil strip ? 30000 m3 sub so