Barking Power reduces plant downtime and enhances operator safety using Emerson’s wireless vibration transmitter
Barking Power reduces plant downtime and enhances operator safety using Emerson’s wireless vibration transmitter
For more information: www.emerson.com/ams POWER Barking Power reduces plant downtime and enhances operator safety using Emerson’s wireless vibration transmitter RESULTS • Avoided potential repair cost of £200,000 by preventing failure • Prevented potential loss of revenue of up to £50,000/day • Early detection of machine problems prevents catastrophic failures • Enhanced operator safety • Increased the efficiency of maintenance resources APPLICATION Temporary vibration monitoring of a starting motor housed in a gas turbine auxiliary compartment. CUSTOMER Barking Power Station outside of London has a capacity of 1000MW and is one of the largest independently-owned generating plants in the UK. CHALLENGE A gas turbine starting motor was being monitored using a handheld collector w