The Challenge Atkins won the contract with Network Rail for the replacement of the signalling on the Newport line and then turned to Unipart Rail for 15 fully fitted Relocatable Equipment Buildings (REBs) and 130 Location Cases for the contract. The Solution Unipart Rail’s Crewe and York Service Centres used Atkins’ designs to develop a manufacturing phased delivery schedule which spanned eight months, and was scheduled from February to S