Case Study
Asbestos Removal
Project Title Value Programme Duration Nature Client Prestigious Central London Theatre £250,000.00 8 Weeks Asbestos Removal Overbury plc About The Project Overbury plc were the principal contractor for the scheme to refurbish this prestigious theatre and appointed Decontaminate to undertake the asbestos abatement. Our team carefully and safely removed asbestos from within the main auditorium and ancillary areas. Due to the significant height within the auditorium it was necessary to construct a fixed scaffold upon which our enclosure was erected. Contaminated masonry and ductwork was removed as part of the abatement process. Material removed: - Sprayed asbestos residue - Contaminated masonry - Contaminated mechanical services - Asbestos containing floor tiles - Asbestos flash guard