CASE STUDY: NCC HOUSING SCHEME MAIN CONTRACTOR: ROBERT WOODHEAD LTD START DATE: OCTOBER 2016 END DATE: APRIL 2018 CONTRACT VALUE: £729,310.74 PACKAGE: MECHANICAL & ELECTRICAL LOCATION: VARIOUS SITES NOTTINGHAM - 79 HOUSES AND COMMUNAL AREAS PROJECT DESCRIPTION 79 new properties being built, as part of the Building a Better Nottingham scheme. The programme was delivered across the city in partnership with Nottingham City Homes (NCH), Nottingham City Council (NCC). the project has seen the construction of 60 bungalows 13 houses and 6 communal bungalows contributing to a commitment to build 100 new bungalows by 2019. The bungalows will offer quality homes for older people or those with mobility issues, enabling them to move into suitable accommodation while remaining