Case Study
Airbus – Paint Shop Enabling Works
33-35 SANDY LANE, SKELMERSDALE, LANCS, WN8 8LA T 01635 555065 E info@hawkinsconstruction.co.uk W www.hawkinsconstruction.co.uk Airbus – Paint Shop Enabling Works Programme: 14 Weeks Form Of Contract: NEC 3 With Amendments Project Value: £430K Location: Airbus UK, Broughton Project Description: Hawkins Construction (Northern) Limited was instructed by Air Bus to carry out Enabling works to their on-site paint shop:- • Erecting of temporary dust screen underneath existing mezzanine floor, breaking out and forming new pit within screened off area. • New chimney base and support steel work and penetrations within cladding. • New steel stair case. • Form new external drainage and alterations to existing drainage and services alterations.