Case Study

Air-conditioning at Green Gold Complex, Croatia

Air-conditioning at Green Gold Complex, Croatia

Pages 2 Pages

Air-conditioning at Green Gold Complex, Croatia Project Overview The project comprises of supply of 350 TR (1230 kW) cooling & 460 kW heating Exhaust + Jacket water driven Chiller-heaters to be installed at the Gold field complex in Zagreb , Croatia for air conditioning application using waste heat recovery from 2nos x 637 kW gas engine Project Description The Green Gold Complex is a commercial centre located in the hub of Zagreb city in Croatia. Two GE Jenbacher engines of 637 kW capacity each are set up at this site for captive power consumption. Although there are no power issues here in Zagreb , the contractors believe in providing the utilities & metering the operating cost. The chillers would provide chilled water for air- conditioning during summer seas